Hello viewers, In this video I've done the detailed estimate of aqueduct of a minor.
Here the description of works are:
1. earthwork excavation
2. PCC work
3. Brick work

This type of question is generally asked for 16 marks in Diploma in Civil Engineering. Watch this video and learn about detailed estimate of a aqueduct of a minor and try to solve it with your own.
If you have any querry comment down below or email me.
Email link is in bio.

#Aqueduct_of_Minor #Estimate #Civil_Engineering

Thank You for Watching.