Direct Materials Variances
11.2 هزار بار بازدید -
4 سال پیش
-
The formulas for the direct
The formulas for the direct materials variances are as follows.
Total materials variance
= (Actual quantity × Actual price) − (Standard quantity × Standard price)
Materials price variance
= (Actual quantity × Actual price) − (Actual quantity × Standard price)
Materials quantity variance
= (Actual quantity × Standard price)−(Standard quantity × Standard price)
Total materials variance
= (Actual quantity × Actual price) − (Standard quantity × Standard price)
Materials price variance
= (Actual quantity × Actual price) − (Actual quantity × Standard price)
Materials quantity variance
= (Actual quantity × Standard price)−(Standard quantity × Standard price)