Direct Materials Variances

Professor Bossard
Professor Bossard
11.2 هزار بار بازدید - 4 سال پیش - The formulas for the direct
The formulas for the direct materials variances are as follows.    
Total materials variance
= (Actual quantity × Actual price) − (Standard quantity × Standard price)

Materials price variance
= (Actual quantity × Actual price) − (Actual quantity × Standard price)

Materials quantity variance
= (Actual quantity × Standard price)−(Standard quantity × Standard price)