In this video, Dan from School of Sheets shows you different ways to determine the percent complete of your Projects at the project level using hierarchy, formulas, and sheet summary fields.

💻 FUNCTIONS USED
➣ =AVG(CHILDREN())
➣ =AVG([% Complete]:[% Complete])
➣ As a bonus, MIN() and MAX() are used to pull in the earliest start date and latest end date for the project via =MIN(CHILDREN()) and =MAX(CHILDREN())

🏢 ABOUT SCHOOL OF SHEETS
➔ We are a bespoke consulting firm specializing in developing custom Smartsheet Solutions
➔ We are a Smartsheet Aligned Gold partner with a team of certified consultants and software developers.
➔ We work with businesses of all sizes and industries.
➔ Learn more at http://www.schoolofsheets.com

🤝 WANT TO WORK WITH US?
Fill out our new client interest form at https://www.schoolofsheets.com/WorkWi...

📚 KEY RESOURCES
➔ Try Smartsheet free for 30-days http://www.schoolofsheets.com/TrySmar...

🔔 SUBSCRIBE FOR MORE GREAT CONTENT
👉 @schoolofsheets

⌚ TIMESTAMPS
00:00 – Intro
00:20 – Example Sheet and Data
00:58 – Using Hierarchy
04:27 – Using Smartsheet Project Settings
07:10 – Using Sheet Summary Fields without Hierarchy
08:45 – Summary