CeTeau Wickdrain record project
9.6 هزار بار بازدید -
9 سال پیش
-
Installation of close to 13.000.000
Installation of close to 13.000.000 meter vertical drain in less than 2 months. CeTeau has completed a large soil improvement project in Port Dickson, Malaysia for a new power plant of Jimah East Power.
A sand platform of 54 hectares was reclaimed above the high water level to create a working platform. CeTeau has installed some 13 million meter Prefabricated Vertical Drains (PVD) from this platform. The PVD were installed at a triangular spacing of 1.0m to a depth of 27 meters.
A view from the sky using the latest drone from DJI.
A sand platform of 54 hectares was reclaimed above the high water level to create a working platform. CeTeau has installed some 13 million meter Prefabricated Vertical Drains (PVD) from this platform. The PVD were installed at a triangular spacing of 1.0m to a depth of 27 meters.
A view from the sky using the latest drone from DJI.
9 سال پیش
در تاریخ 1394/12/25 منتشر شده
است.
9,636
بـار بازدید شده