44.7 هزار بار بازدید - 4 سال پیش - The NITAP Permanent campus Phase
The NITAP Permanent campus Phase 1A has been constructed by CPWD. Total 26 No’s buildings with 55,575sqm plinth area have been constructed in this phase within a Span of about 15 months. Precast Construction technology has been adopted in order to complete this entire project within time. The construction cost including development & bulk services is Rs.37, 171/- per sqm which is far below than cost of construction of other NIT’s and IIT’s being undertaken in a similar time. Planning, Designing & Execution by Central Public Works Department(CPWD) Agency: M/s BG Shirke Construction Technology Pvt. Ltd.