Road Quantity estimation of earthwork for embankment | Mean depth method | Quantity survey
4.8 هزار بار بازدید -
3 سال پیش
-
To understand the mean depth
To understand the mean depth method to find out the quantity estimation of earthwork for 150 m length of embankment let's solve the following numerical example. It is given that
Work out the quantity of earthwork for an embankment. The top width of this bank is 2 m. 1.5 m down from the top is a 3m wide berm is to be provided on one side of the bank. The side slope on the berm side is 1:1 whereas on another side 2:1. The top-level of the bank is proposed as 265 m and Natural Surface Levels at 30 m interval is given.
For the solution watch, the video tell end.
#quantitysurvey
#roadestimation
#civilengineeringvideos
#meandepthmethod
#estimation
#roadprofile
#roadconstruction
#roadsection
Work out the quantity of earthwork for an embankment. The top width of this bank is 2 m. 1.5 m down from the top is a 3m wide berm is to be provided on one side of the bank. The side slope on the berm side is 1:1 whereas on another side 2:1. The top-level of the bank is proposed as 265 m and Natural Surface Levels at 30 m interval is given.
For the solution watch, the video tell end.
#quantitysurvey
#roadestimation
#civilengineeringvideos
#meandepthmethod
#estimation
#roadprofile
#roadconstruction
#roadsection
3 سال پیش
در تاریخ 1400/02/08 منتشر شده
است.
4,835
بـار بازدید شده