Network Analysis - Delays and Changes to the Critical Path
28.4 هزار بار بازدید -
6 سال پیش
-
What happens to a project
What happens to a project completion time and the critical path if one or more activities are delayed? The answer is - the overall effect depends on whether those activities were on the original critical path. This video provides a simple worked example to illustrate the effect of activity delays.