Erection Sequence of Vertical & Horizontal Precast Elements |Installation Methodology |

Construction Technology
Construction Technology
116 بار بازدید - 2 هفته پیش - 1. Prepare the permit and
1. Prepare the permit and Safety documents
2. Approved and sufficient capacity of mobile/crawler crane is usr
3.Lifting area is fully barricaded and signboard placed
4.precast vehicle movement will be controlled by a banks  man or flag man
5.Truck is placed near the crane
6.Lifting supervisor or rigger inspect load lifting gear lifting point proor to start
7.Tagline is attached to the elements for controlling movements
8.Precast element is moved to designated position
9. panel adjusted to correct position and secure with props
10. Alignment and verticality of panel
11.finall stability of props by supervisor or formam