VDOT: Interstate 81 In-Place Pavement Recycling
33 هزار بار بازدید -
12 سال پیش
-
Using three pavement recycling processes
Using three pavement recycling processes together on a single rehabilitation project on the U.S. interstate system had never been done -- until Virginia did it in 2011.
VDOT employed full-depth reclamation, cold central-plant recycling and cold in-place recycling to rebuild a 3.7-mile, two-lane section of southbound Interstate 81 near Staunton.
The agency reduced its estimated construction time by two-thirds and saved millions of dollars by using the three pavement recycling methods to reconstruct this part of the interstate.
Visit http://www.virginiadot.org
VDOT employed full-depth reclamation, cold central-plant recycling and cold in-place recycling to rebuild a 3.7-mile, two-lane section of southbound Interstate 81 near Staunton.
The agency reduced its estimated construction time by two-thirds and saved millions of dollars by using the three pavement recycling methods to reconstruct this part of the interstate.
Visit http://www.virginiadot.org
12 سال پیش
در تاریخ 1391/02/04 منتشر شده
است.
33,054
بـار بازدید شده