Primavera P6 Multiple Float Paths - Layout by Total Float

indiana1917
indiana1917
18.1 هزار بار بازدید - 10 سال پیش - Multiple float path scheduling setup
Multiple float path scheduling setup and layout.  This layout groups by total float rather than Primavera's "Float Path" to lessen confusion in large projects.  The sample project's most critical activities have -14 days of float, are grouped as such, with the group title -14. The Float Path group would have the group title of 1.